| ID | 65434 |
|---|---|
| Project ID | 23328 |
| Project Step | 6 |
| Project Year | 2568 |
| Step Detail | ดำเนินการปรับปรุงกายภาพโรงเรียนที่ 4 เรียบร้อยแล้ว |
| Step Percent | 15 |
| Step Start | 01-01-2025 |
| Step End | 31-08-2025 |
| Note | (not set) |
| Created At | 31-10-2024 00:00:00 |
| Updated By | 74 |
| Created By | 934 |
| Updated At | 04-08-2025 00:00:00 |
| Status Lock | Y |
| Step Sum | 80 |
| Project Name | (not set) |
| Step Status | 0 |
| Step Reporter | (not set) |
| Project Id1 | (not set) |
| Report Now | 15 |
| Report Note | (not set) |
| Report Date | 04-08-2025 08:45:05 |
| Sed Approved | 1 |
| Sed Approve By | 934 |
| Sed Approve At | 25-08-2025 09:47:15 |
| Sed Commentnote | (not set) |
| Subdepart Id Responsible | (not set) |