| ID | 48602 |
|---|---|
| Project ID | 9531 |
| Project Step | 6 |
| Project Year | 2568 |
| Step Detail | ดำเนินงานตามโครงการ |
| Step Percent | 20 |
| Step Start | 01-10-2024 |
| Step End | 30-09-2025 |
| Note | (not set) |
| Created At | 25-10-2024 00:00:00 |
| Updated By | 11119 |
| Created By | 2339 |
| Updated At | 23-05-2025 00:00:00 |
| Status Lock | Y |
| Step Sum | 90 |
| Project Name | (not set) |
| Step Status | 0 |
| Step Reporter | (not set) |
| Project Id1 | (not set) |
| Report Now | 20 |
| Report Note | (not set) |
| Report Date | 23-05-2025 11:22:15 |
| Sed Approved | 1 |
| Sed Approve By | 11119 |
| Sed Approve At | 13-08-2025 17:55:38 |
| Sed Commentnote | (not set) |
| Subdepart Id Responsible | (not set) |